Work out what one machine hour costs you and what to charge for it, in the costing order contractors know: ownership per year, per billable hour, running costs per hour, surcharge, price per hour. Every figure is your own, and each attachment gets its own add-on rate.
Attachment Warehouse · Optional
Attachments for this job
Hammers, auger drives and grapples are the attachments most often priced as their own hourly add-on. Enter yours under Attachments.
How it works
- 01
Enter purchase price, one-off costs, useful life, residual value, interest and repair factor. Depreciation, interest and repairs per year appear as you type.
- 02
Enter the hours you can bill in a year, then operator wage, fuel use and diesel price, oil and AdBlue, wear parts and other costs per hour.
- 03
Add overheads and profit to get the price per hour. Save it to the job, use it as a machine line in the job cost sheet or compare buying with hiring.
Formula
Depreciation = (acquisition − residual) ÷ years. Interest = (acquisition + residual) ÷ 2 × rate. Repairs = depreciation × repair factor.
Cost per hour = ownership per year ÷ billable hours + operator + fuel + oil and AdBlue + wear and other.
Price per hour = cost per hour × (1 + overheads) × (1 + financing) × (1 + risk) × (1 + profit).
Load labelled example
The public WKO brochure example: 100,000 purchase plus 5,000 one-off, 6 years, 30,000 residual, 5 % interest, repair factor 0.6, 1,000 fixed costs and 1,200 hours give ownership of 20.31 per hour. With operator, fuel and other costs the cost is 71.91 per hour, and after 15, 0.5, 6 and 5 % surcharges the price is 92.50 per hour.